Phase 1 – Connectivity Buildout (DAL & ASH)
Scope: AWS Production and Non-Production
- Provision the AWS Direct Connect connections through Equinix.
- Complete Cisco WAN interface and VLAN configurations.
- Bring up Layer 3 connectivity.
- Validate point-to-point connectivity using ICMP.
- Establish BGP peering for both Prod and Non-Prod.
- Keep production route advertisements and acceptance disabled (NO ROUTING).
- Validate BGP session stability, BFD, and connectivity redundancy.
Outcome: All AWS connections are operational and BGP sessions are established without introducing production routing changes.
Phase 2 – Multi-Cloud Routing Design Alignment
Scope: AWS, Azure, and GCP
Before enabling routing, coordinate with all three cloud teams to establish a consistent routing strategy.
- AWS: Confirm routing preferences for DAL and ASH relative to existing CHI and NY connectivity.
- Azure: Coordinate the ASH ExpressRoute buildout and routing activation.
- GCP: Account for the upcoming Partner Interconnect deployment and its regional routing design.
- Confirm whether ASH should be the preferred path for both AWS and Azure.
- Review BGP path selection, AS-path prepending, route advertisements, and failover behavior.
- Establish and document primary, secondary, and tertiary routing preferences for each cloud.
- Confirm routing symmetry requirements and expected failover behavior.
Outcome: All cloud teams agree on the intended routing architecture before any production routing changes.
Phase 3 – Routing Activation and Validation
Scope: AWS Production and Non-Production, coordinated with Azure
- Schedule routing changes through the change-management process.
- Coordinate AWS and Azure routing activation, particularly for ASH.
- Enable approved BGP route advertisements and acceptance.
- Validate route propagation and preferred traffic paths.
- Test failover between Equinix locations.
- Confirm traffic follows the documented routing preferences.
- Monitor stability and performance following activation.
Outcome: DAL and ASH are integrated into the production routing architecture with validated path selection and resiliency.
Key Dependencies
- AWS DAL and ASH connectivity must be established and validated before routing activation.
- Azure ASH connectivity and routing readiness must be coordinated with AWS.
- The cloud teams must confirm whether ASH is the preferred location.
- Routing preferences must be documented and agreed upon before scheduling changes.
- GCP’s future connectivity should be considered to maintain a consistent multi-cloud architecture.
Important: Infrastructure provisioning and BGP validation can proceed independently. Production routing activation remains dependent on multi-cloud routing alignment.